Complete Home Construction Project Sample
The following outline is for a 32’x60′ 2 Storey Building with 4 bedrooms and 3 toilets and bath.
SHED & LINE UP
1 DAY
- Clean lot
- Build shed
- Set up tank for water
- Electricity (Owner responsibility)
- Line up building
FOUNDATION & SLAB
30 DAYS
- Tie steel
- Pile, matt, column, ground beam, top beam, ring beam
- Square hole – 5 days
- Trenches – 5 days
- Pile auger
- Put in steel and cast pile, matt ground beam – 2 days
- Build starter boxing – 2 days
- Cast – 3 days
- Put down 6” or 8” concrete blocks and cast – 3 days
- Backfill (20-30 loads) – 5 days
- Compact – 1 days
- Lay polythene, BRCm steel, raise – 3 days
- Electrical & Plumbing
- Cast slab 5” lath install around slab
SUPERSTRUCTURE – FRAMES, SLABS, STEPS
16 DAYS
- Build column boxing – 2 days
- Install, cast columns – 2 days
- Build decking – 10 days
- Tie steel
- Install top beams – 2 days
- Put ½ steel, 6” apart both ways
- Raise floor
- Electrical & Plumbing
- Cast slab, install 5” lath around, slab
FIRST FLOOR
14 DAYS WORK
- Install profile – 2 days
- Block upstairs – 14 days
- Build window heads, install steel – 2 days
- Build door head, install steel – 1 day
- Build ring beam, install steel pipes, cans – 1 day
- Install door frames – 3 days
- Breakout decking
FRAME ROOF
12 DAYS WORK
- I beam
- 2 purlin
- Sheet roof – 5 days
- Heat protection – 5 days
30 DAYS WORK
- Company install scaffolding
- Plaster interior and exterior of house, upstairs – 30 days
- Install plumbing in walls – 3 days
- Install steel windows – 3 days
- Floors
57 DAYS WORK
- Prime house – 10 days
- Tile toilet and bath – 7 days
- Last coat – 10 days
- Tiling of floors – 7 days
- Install plumbing fixtures – 3 days
- Cupboards, doors, aluminum windows, designer door – 3 days
- Cast drain, driveway, pavement – 7 days
- Build cesspit and soakway – 2 days
- Fencing, chainlink, ½ walls, wrought iron – 10 days
- Clean site