21 Mar 2014admin0 CommentsPost Slider Single House Construction Schedule (Example) Schedule of stages in typical single house construction. Plans, Financing, PermitsPlans, financing and permits as well as any other aspects of the pre-construction stage will have a variable duration depending on site and house characteristics.Layout of BuildingTwo DaysExcavation and FootingsFour DaysFoundations, Drainage and BackfillOne WeeksFraming (includes roofing and flashing)Two WeeksDoors and WindowsOne WeekExterior Finishes”Plumbing, Two WeeksInsulation, Air and Vapour BarriersTwo WeeksInterior FinishesTwo WeeksPaint, Cabinets and FixturesTwo WeeksLandscapingOne Week