Single House Construction Schedule (Example)
Schedule of stages in typical single house construction.
Plans, Financing, Permits
Plans, financing and permits as well as any other aspects of the pre-construction stage will have a variable duration depending on site and house characteristics.
Layout of Building
Two Days
Excavation and Footings
Four Days
Foundations, Drainage and Backfill
One Weeks
Framing (includes roofing and flashing)
Two Weeks
Doors and Windows
One Week
Exterior Finishes
”Plumbing,
Two Weeks
Insulation, Air and Vapour Barriers
Two Weeks
Interior Finishes
Two Weeks
Paint, Cabinets and Fixtures
Two Weeks
Landscaping
One Week